    Equipped with one of the best sinter cooler waste heat recovery boiler brands, JSDJ Heavy Industry Co.,Ltd is one of the professional quality sinter plant waste heat recovery system, waste heat recovery boiler in steel plant, sinter cooler waste heat recovery system manufacturers in China.

    Sinter Cooler Waste Heat Recovery Boiler

    Necessity

    Sinter Cooler process is highly energy consuming and it accounts for 10% of the entire energy input in steel making process. Moreover, 50% of the energy being consumed in this very process is lost in the environment in the form of emitting waste flue gas into our atmosphere. It is due to both equipment inefficiencies and thermodynamic limitations of the equipment. Recovering waste heat emanated from this process makes sense for both environmental sustainability and prospective economical benefits. 

    Design Ingenuity

    Our boiler adopts inner thermal insulation pipe-box type structure to eliminate direct contact between flue gas and box steel frame. This structure not only ensures the safety of heat surface tube-box frame but also minimizes air leakage which is to lower heat loss & power consumption of induced draft fan, and increase overall operational efficiency. Heat surface adopts spiral finned tubes with high finned ratio & small diameter. This design enhances heat transfer and increases abrasion resistance. Also, all weld seam and elbow are located outside the gas passage which guarantees the long term safe operation of heat surface and provides convenience for maintenance. The average investment recovery period is only 1.8 years.

    Key Parameters 

    1 T Iron Ore = 120 KG ~ 150 KG of steam output  

    HP pressure: 1.0 MPA ~ 2.5 MPA

    HP steam temp: saturated steam temp ~ 380?

    LP steam pressure: 0.3 MPA ~ 0.8 MPA

    LP steam temp: saturated steam temp ~ 260?


    PROJECT SINTER COOLER 550 m2 WASTE HEAT RECOVERY FOR: 

    BAOSTEEL GROUP CO., LTD. - ZHANJIANG PLANT

    HP steam output: 65 T / H @ 1.8 MPA 

    HP steam temp: 360 Deg Celsius 

    LP steam output: 20 T / H @ 0.4 MPA 

    LP steam temp: 180 Deg Celsius (saturated temp)

    PROJECT SINTER COOLER 360 m2 WASTE HEAT RECOVERY FOR:

    JIANGSU SHAGANG CO., LTD. (SHA-STEEL)

    HP steam output: 45 T / H @ 1.57 MPA 

    HP steam temp: 320 Deg Celsius 

    LP steam output: 14 T / H @ 0.35 MPA 

    LP steam temp: 147.9 Deg Celsius (saturated temp)

    PROJECT SINTER COOLER 360 m2 WASTE HEAT RECOVERY FOR:

    XIANGTAN IRON & STEEL GROUP CO., LTD. 

    HP steam output: 43 T / H @ 1.8 MPA 

    HP steam temp: 370 Deg Celsius 

    LP steam output: 10.5 T / H @ 0.5 MPA 

    LP steam temp: 158.8 Deg Celsius (saturated temp)

Send your message to this supplier
To:  

JSDJ Heavy Industry Co.,Ltd.

* Content:  

For better quotations, include:

- A self introduction

- Special requests, if any

Quantity:  

  
Not exactly what you want? One request, multiple quotations Get Quotations Now >>